==Roadmap== | ==Roadmap== | ||
=== | ===Phase 1: wrap up and ship a summary=== | ||
* '''Jul 31''' - (DONE) '''wiki updated.''' this wiki is updated and provides a single clear home for the work | * '''Jul 31''' - (DONE) '''wiki updated.''' this wiki is updated and provides a single clear home for the work | ||
* '''Aug 4''' - (DONE) '''working group documents.''' all three Phase 2 working groups have a single canonical home on the wiki that they can own and drive forward | * '''Aug 4''' - (DONE) '''working group documents.''' all three Phase 2 working groups have a single canonical home on the wiki that they can own and drive forward | ||
* '''Aug 10''' - (DONE) '''communications plan'''. with talking points for staff meeting are drafted and ready for review | * '''Aug 10''' - (DONE) '''communications plan'''. with talking points for staff meeting are drafted and ready for review | ||
=== | ===Phase 2: ship the draft strategy=== | ||
With two key deliverables: | With two key deliverables: | ||
# '''a detailed draft strategy'''. merging our completed Google Docs into a single strategy book. | # '''a detailed draft strategy'''. merging our completed Google Docs into a single strategy book. | ||
| Line 61: | Line 61: | ||
* '''Oct 14''' - present to board | * '''Oct 14''' - present to board | ||
=== | ===Phase 3: ship the completed business plan, with roadmaps and budgets=== | ||
* '''Oct 20''' - report-back from Board. Kick off Phase 3. | * '''Oct 20''' - report-back from Board. Kick off Phase 3. | ||
* '''Nov 6 - 8''' - MozFest. Get feedback on the plan. | * '''Nov 6 - 8''' - MozFest. Get feedback on the plan. | ||