=Photon Project Status Updates= | =Photon Project Status Updates= | ||
<p> </p> | <p> </p> | ||
==Tuesday June | ==Tuesday June 13, 2017== | ||
<sub>''Note: Updated every Tuesday.''</sub> | <sub>''Note: Updated every Tuesday.''</sub> | ||
<p> </p> | <p> </p> | ||
| Line 9: | Line 9: | ||
===Visual Redesign Team=== | ===Visual Redesign Team=== | ||
* In Development. | * In Development. | ||
* Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release II] (May 23 - July 3) with | * Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release II] (May 23 - July 3) with 89% of the release goal completed. | ||
* Team has [http://tinyurl.com/mf4u59q completed | * Team has [http://tinyurl.com/mf4u59q completed 57%] of the Project MVP Backlog. | ||
* On track for completion of the [http://tinyurl.com/kv4ufsf Project MVP Backlog] for Release 57. | * On track for completion of the [http://tinyurl.com/kv4ufsf Project MVP Backlog] for Release 57. | ||
* QA has [http://tinyurl.com/mcu9cdd verified | * QA has [http://tinyurl.com/mcu9cdd verified 34%] of all Project MVP Backlog work requiring testing. | ||
* [http://tinyurl.com/n5utsok Project Reserve Backlog] contains 12 work items: 8 unassigned, 1 assigned and 3 completed. | * [http://tinyurl.com/n5utsok Project Reserve Backlog] contains 12 work items: 8 unassigned, 1 assigned and 3 completed. | ||
<p> </p> | <p> </p> | ||
===Performance Team=== | ===Performance Team=== | ||
* In Development. | * In Development. | ||
* Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release II] (May 23 - July 3) with | * Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release II] (May 23 - July 3) with 100% of the release goal completed. | ||
* Team has [http://tinyurl.com/k3cmwj3 completed | * Team has [http://tinyurl.com/k3cmwj3 completed 70%] of the Project MVP Backlog. | ||
* On track for completion of the [http://tinyurl.com/l7lhk8h Project MVP Backlog] for Release 57. | * On track for completion of the [http://tinyurl.com/l7lhk8h Project MVP Backlog] for Release 57. | ||
* QA has [http://tinyurl.com/ms9cyu9 verified 9%] of all Project MVP Backlog work requiring testing. | * QA has [http://tinyurl.com/ms9cyu9 verified 9%] of all Project MVP Backlog work requiring testing. | ||
* [http://tinyurl.com/k3mcbl6 Project Reserve Backlog] contains 118 work items: | * [http://tinyurl.com/k3mcbl6 Project Reserve Backlog] contains 118 work items: 87 unassigned, 10 assigned and 21 completed. | ||
<p> </p> | <p> </p> | ||
===Structure Team=== | ===Structure Team=== | ||
* In Development. | * In Development. | ||
* Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release II] (May 23 - July 3) with 100% of the release goal completed. | * Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release II] (May 23 - July 3) with 100% of the release goal completed. | ||
* Team has [http://tinyurl.com/m2gptop completed | * Team has [http://tinyurl.com/m2gptop completed 73%] of the Project MVP Backlog. | ||
* On track for completion of the [http://tinyurl.com/lvxaml6 Project MVP Backlog] for Release 57. | * On track for completion of the [http://tinyurl.com/lvxaml6 Project MVP Backlog] for Release 57. | ||
* QA has [http://tinyurl.com/lytzlyk verified | * QA has [http://tinyurl.com/lytzlyk verified 47%] of all Project MVP Backlog work requiring testing. | ||
* [http://tinyurl.com/leajt7r Project Reserve Backlog] contains | * [http://tinyurl.com/leajt7r Project Reserve Backlog] contains 29 work items: 24 unassigned, 0 assigned and 5 completed. | ||
<p> </p> | <p> </p> | ||
===Animation Team=== | ===Animation Team=== | ||
* In Development. | * In Development. | ||
* Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release II] (May 23 - July 3) with 100% of the release goal completed. | * Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release II] (May 23 - July 3) with 100% of the release goal completed. | ||
* Team has [http://tinyurl.com/kt8s9ej completed | * Team has [http://tinyurl.com/kt8s9ej completed 44%] of the Project MVP Backlog. | ||
* On track for completion of the [http://tinyurl.com/n6fdhbq Project MVP Backlog] for Release 57. | * On track for completion of the [http://tinyurl.com/n6fdhbq Project MVP Backlog] for Release 57. | ||
* QA has [http://tinyurl.com/mbk5vxm verified | * QA has [http://tinyurl.com/mbk5vxm verified 42%] of all Project MVP Backlog work requiring testing. | ||
* [http://tinyurl.com/la6qgyf Project Reserve Backlog] contains | * [http://tinyurl.com/la6qgyf Project Reserve Backlog] contains 13 work items: 12 unassigned and 1 assigned and 0 completed. | ||
<p> </p> | <p> </p> | ||
===Onboarding Team=== | ===Onboarding Team=== | ||
| Line 50: | Line 50: | ||
* In Development. | * In Development. | ||
* Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release II] (May 23 - July 3) with 100% of the release goal completed. | * Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release II] (May 23 - July 3) with 100% of the release goal completed. | ||
* Team has [https://goo.gl/uTLWY4 completed | * Team has [https://goo.gl/uTLWY4 completed 69%] of the Project MVP Backlog. | ||
* On track for completion of the [https://mzl.la/2q4ueEN Project MVP Backlog] for Release 57. | * On track for completion of the [https://mzl.la/2q4ueEN Project MVP Backlog] for Release 57. | ||
* QA has [http://tinyurl.com/legpcdq verified | * QA has [http://tinyurl.com/legpcdq verified 34%] of all Project MVP Backlog work requiring testing. | ||
* [https://mzl.la/2q4mceY Project Reserve Backlog] contains | * [https://mzl.la/2q4mceY Project Reserve Backlog] contains 16 work items: 16 unassigned, 0 assigned and 0 completed. | ||