Changes

Jump to: navigation, search

Firefox/Photon/Updates

915 bytes removed, 18:15, 15 August 2017
no edit summary
=Photon Project Status Updates=
<p> </p>
==Tuesday August 815, 2017==
<sub>''Note: Updated every Tuesday.''</sub>
<p> </p>
===Visual Redesign Team===
* In Development.
* Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release IIIIV] (July 4 August 15 - August 14September 15) with 15210% of the release goal completed.* Team has [http://tinyurl.com/mf4u59q completed 8595%] of the Project MVP Backlog.
* On track for completion of the [http://tinyurl.com/kv4ufsf Project MVP Backlog] for Release 57.
* QA has [http://tinyurl.com/mcu9cdd verified 3650%] of all Project MVP Backlog work requiring testing.* Team's goal is to complete [httphttps://tinyurlmzl.comla/n5utsok Project Reserve Backlog] contains 54 2x1xH9j 15 high priority reserve work items: 43 unassigned, 6 assigned and 5 completed] in the final release.
<p> </p>
===Performance Team===
* In Development.
* Team is working members currently on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release III] (July 4 PTO - update to be provided on Wednesday August 14) with 127% of the release goal completed.* Team has [http://tinyurl.com/k3cmwj3 completed 86%] of the Project MVP Backlog.* On track for completion of the [http://tinyurl.com/l7lhk8h Project MVP Backlog] for Release 57.* QA has [https://mzl.la/2sQiOVI verified 36%] of all Project MVP Backlog work requiring testing.* [http://tinyurl.com/k3mcbl6 Project Reserve Backlog] contains 130 work items: 77 unassigned, 15 assigned and 38 completed16.
<p> </p>
===Structure Team===
* In Development.
* Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release IIIIV] (July 4 August 15 - August 14September 15) with 18313% of the release goal completed.* Team has [http://tinyurl.com/m2gptop completed 8590%] of the Project MVP Backlog.
* On track for completion of the [http://tinyurl.com/lvxaml6 Project MVP Backlog] for Release 57.
* QA has [http://tinyurl.com/lytzlyk verified 7074%] of all Project MVP Backlog work requiring testing.* Team's goal is to complete [httphttps://tinyurlmzl.comla/leajt7r Project Reserve Backlog] contains 79 2x1pl1m 4 high priority reserve work items: 60 unassigned, 5 assigned and 14 completed] in the final release.
<p> </p>
===Animation Team===
* In Development.* Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release III] (July 4 - August 14) with 150% of the release goal completedMVP Completed.* Team has [http://tinyurl.com/kt8s9ej completed 94100%] of the Project MVP Backlog.* On track for completion of the [http://tinyurl.com/n6fdhbq Project MVP Backlog] for Release 57.* QA has [http://tinyurl.com/mbk5vxm verified 5091%] of all Project MVP Backlog work requiring testing.* Team's goal is to complete [httphttps://tinyurlmzl.comla/la6qgyf Project Reserve Backlog] contains 59 2x19PCD 6 high priority reserve work items: 26 unassigned and 5 assigned and 28 completed] in the final release.
<p> </p>
===Onboarding Team===
* In Development.
* Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release IIIIV] (July 4 August 15 - August 14September 15) with 17625% of the release goal completed.* Team has [https://mzl.la/2so1BCW completed 8396%] of the Project MVP Backlog.
* On track for completion of the [https://mzl.la/2tGWwcL Project MVP Backlog] for Release 57.
* QA has [https://mzl.la/2wFYEzc verified 6878%] of all Project MVP Backlog work requiring testing.* [https://mzl.la/2q4mceY Project Reserve Backlog] contains 20 work items: 8 assigned and 12 completedupdate will be made available on Friday August 18.
<p> </p>
===Preference Team===
* In Development.
* Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release IIIIV] (July 4 August 15 - August 14September 15) with 2380% of the release goal completed.
* Team has [https://mzl.la/2wFXvHU completed 92%] of the Project MVP Backlog.
* On track for completion of the [https://mzl.la/2q4ueEN Project MVP Backlog] for Release 57.
* QA has [https://mzl.la/2q4ueEN verified 6263%] of all Project MVP Backlog work requiring testing.* [https://mzl.la/2so3v6u Project Reserve Backlog] contains 28 work items: 22 unassigned and 4 assigned and 2 completedupdate will be made available on Friday August 18.