Below is a weekly engineering development update. | Below is a weekly engineering development update. | ||
<p> </p> | <p> </p> | ||
==== | ==== July 3 Update ==== | ||
<p> </p> | <p> </p> | ||
* Status: '''Green''' - In Development. | * Status: '''Green''' - In Development. | ||
* Team is [https://mzl.la/2GoDoCJ currently working on Iteration #7] which runs from June 25 - July 6. | * Team is [https://mzl.la/2GoDoCJ currently working on Iteration #7] which runs from June 25 - July 6. | ||
* A cumulative completion of 41 bugs is required by the conclusion of Iteration #7 to remain on schedule. | * A cumulative completion of 41 bugs is required by the conclusion of Iteration #7 to remain on schedule. | ||
* Team has, to date, a cumulative completion of | * Team has, to date, a cumulative completion of 42 bugs for Iteration #7. | ||
* Team has [https://mzl.la/2HyVqTB completed | * Team has [https://mzl.la/2HyVqTB completed 84%] of the entire [https://mzl.la/2pe4jLM Milestone 1 - 3 Backlog]. | ||
* The forecast completion of the entire Milestone 1 - 3 Backlog is on August 17. | * The forecast completion of the entire Milestone 1 - 3 Backlog is on August 17. | ||
* View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog. | * View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog. | ||
[[File:WPD CurrentUpdateNow.png|frame|center|Updated Weekly. Current Update - Monday, | [[File:WPD CurrentUpdateNow.png|frame|center|Updated Weekly. Current Update - Monday, July 3.]] | ||