| Below is a weekly engineering development update. | | Below is a weekly engineering development update. |
| <p> </p> | | <p> </p> |
| ==== September 11 Update ==== | | ==== September 18 Update ==== |
| <p> </p> | | <p> </p> |
| * Status: '''Green''' - In Development. | | * Status: '''Green''' - Planning. |
| * Team is [https://mzl.la/2GoDoCJ currently working on Iteration #12] which runs from September 3 - September 14. | | * Engineering review for user testing preparedness on nightly surfaced additional engineering work. The plan is to push out the current September 28 pref’d on nightly milestone. The team will have an update early next week on the adjusted nightly milestone. |
| * A cumulative completion of 78 bugs is required by the conclusion of Iteration #12 to remain on schedule.
| |
| * Team has, to date, a cumulative completion of 79 bugs for Iteration #12.
| |
| * Team has [https://mzl.la/2HyVqTB completed 96%] of the entire [https://mzl.la/2pe4jLM Milestone 1 - 3 Backlog].
| |
| * The forecast completion of the entire Milestone 1 - 3 Backlog is on September 28.
| |
| * View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog.
| |
| [[File:WPD CurrentUpdateNow.png|frame|center|Updated Weekly. Current Update - Tuesday, September 11.]]
| |