Below is a weekly engineering development update.
Below is a weekly engineering development update.
<p> </p>
<p> </p>
==== September 25 Update ====
==== October 2 Update ====
<p> </p>
<p> </p>
* Status: '''Green''' - In Development.
* Status: '''Green''' - Completed.
* Engineering has completed their review for user testing preparedness on nightly and has added the work to the Backlog.
* Team has completed 100% of the entire [https://mzl.la/2pe4jLM Milestone 1 - 3 Backlog] on [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Monday, October 1].
* Team is [https://mzl.la/2GoDoCJ currently working on Iteration #13] which runs from September 17 - September 28.
* Planning for the M4 Milestone is underway.
* A cumulative completion of 91 bugs is required by the conclusion of Iteration #13 to remain on schedule.
* Team has, to date, a cumulative completion of 90 bugs for Iteration #13.
* Team has [https://mzl.la/2HyVqTB completed 94%] of the entire [https://mzl.la/2pe4jLM Milestone 1 - 3 Backlog].
* The forecast completion of the entire Milestone 1 - 3 Backlog is on October 12.