| Below is a weekly engineering development update. | | Below is a weekly engineering development update. |
| <p> </p> | | <p> </p> |
| ==== September 25 Update ==== | | ==== October 2 Update ==== |
| <p> </p> | | <p> </p> |
| * Status: '''Green''' - In Development. | | * Status: '''Green''' - Completed. |
| * Engineering has completed their review for user testing preparedness on nightly and has added the work to the Backlog.
| | * Team has completed 100% of the entire [https://mzl.la/2pe4jLM Milestone 1 - 3 Backlog] on [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Monday, October 1]. |
| * Team is [https://mzl.la/2GoDoCJ currently working on Iteration #13] which runs from September 17 - September 28.
| | * Planning for the M4 Milestone is underway. |
| * A cumulative completion of 91 bugs is required by the conclusion of Iteration #13 to remain on schedule.
| |
| * Team has, to date, a cumulative completion of 90 bugs for Iteration #13.
| |
| * Team has [https://mzl.la/2HyVqTB completed 94%] of the entire [https://mzl.la/2pe4jLM Milestone 1 - 3 Backlog]. | |
| * The forecast completion of the entire Milestone 1 - 3 Backlog is on October 12.
| |
| * View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog.
| |