== Status Summary == | == Status Summary == | ||
=== Development Update - Milestones | === Development Update - Milestones 4 Delivery === | ||
<p> </p> | <p> </p> | ||
Below is a weekly engineering development update. | Below is a weekly engineering development update. | ||
<p> </p> | <p> </p> | ||
* Status: '''Green''' - In Development. | |||
* Team is working on Iteration #1 which runs from October 8 - October 19. | |||
* Status: '''Green''' - | * Team has, to date, completed 0 out of 5 bugs required by the conclusion of Iteration #1 to remain on schedule. | ||
* Team has completed | * Team has completed 0% of the entire Milestone 4 Backlog which is forecast to be completed on December 21. | ||
* View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit#gid=1990398980 Project Tracking Dashboard] for current schedule progress and backlog. | |||