* Status: '''Green''' - In Development. | * Status: '''Green''' - In Development. | ||
* Team has completed 2 out of 5 bugs required by the conclusion of Iteration #1 (Oct 8 - Oct 19) to remain on schedule. | |||
* Team has | * Team has completed 8% of the entire Milestone 4 Backlog which is forecast to be completed on December 21. | ||
* Team has completed | |||
* View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit#gid=1990398980 Project Tracking Dashboard] for current schedule progress and backlog. | * View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit#gid=1990398980 Project Tracking Dashboard] for current schedule progress and backlog. | ||
* Bugzilla Queries: | |||
** [https://mzl.la/2GoDoCJ Work Currently In Development] | |||
** [https://mzl.la/2FDB7b4 Available Project Work] | |||