*Feedback system: We can rewrite this, put the data in new tables, and host the content in an iframe on wiki pages. [[Support/FeedbackSystem2PRD]] | *Feedback system: We can rewrite this, put the data in new tables, and host the content in an iframe on wiki pages. [[Support/FeedbackSystem2PRD]] | ||
*Neither of these items requires migration of users table, will require some migration of templates, and understanding of Tiki sessions | *Neither of these items requires migration of users table, will require some migration of templates, and understanding of Tiki sessions | ||
*Develop user migration plan | |||
*Develop deployment plan | |||
=== Timeline === | === Timeline === | ||
*5 weeks of development including associated tests | *5 weeks of development including associated tests | ||
*Mid term review at 3 weeks to see if we are on track, what else we need, review scope, etc | *Mid term review at 3 weeks to see if we are on track, what else we need, review scope, etc | ||
*2 weeks QA | *2 weeks QA | ||
* Started week of Feb 8 | * Started week of Feb 8 | ||
* Review week of March 1 | * Due for completion March 15 initial estimate, actual ? | ||
* Review: planned week of March 1, actual March 10 | |||
== Interlude == | == Interlude == | ||
edits