m (added {{Draft}} as we haven't updated the list recently)
Line 64: Line 64:
*Feedback system: We can rewrite this, put the data in new tables, and host the content in an iframe on wiki pages. [[Support/FeedbackSystem2PRD]]  
*Feedback system: We can rewrite this, put the data in new tables, and host the content in an iframe on wiki pages. [[Support/FeedbackSystem2PRD]]  
*Neither of these items requires migration of users table, will require some migration of templates, and understanding of Tiki sessions
*Neither of these items requires migration of users table, will require some migration of templates, and understanding of Tiki sessions
*Develop user migration plan
*Develop deployment plan


=== Timeline ===
=== Timeline ===
*5 weeks of development including associated tests  
*5 weeks of development including associated tests  
*Mid term review at 3 weeks to see if we are on track, what else we need, review scope, etc  
*Mid term review at 3 weeks to see if we are on track, what else we need, review scope, etc  
*2 weeks QA
*2 weeks QA
* Started week of Feb 8
* Started week of Feb 8
* Review week of March 1
* Due for completion March 15 initial estimate, actual ?
* Review: planned week of March 1, actual March 10