* The roadmap for the next few weeks is: release Oct 12, soft freeze two weeks after, hard freeze two weeks after, 3.0rc1 on December 8. | * The roadmap for the next few weeks is: release Oct 12, soft freeze two weeks after, hard freeze two weeks after, 3.0rc1 on December 8. | ||
* Not all tasks from the [[Bugzilla:Roadmap initial roadmap]] for 3.0 will be done on time, such as supporting Oracle, AJAXification, customised statuses and workflow. | * Not all tasks from the [[Bugzilla:Roadmap | initial roadmap]] for 3.0 will be done on time, such as supporting Oracle, AJAXification, customised statuses and workflow. | ||
* We plan 3.0 RC1 to be a real Release Candidate, i.e. with all blockers fixed before releasing it. Else we will call our next release 2.23.4. | * We plan 3.0 RC1 to be a real Release Candidate, i.e. with all blockers fixed before releasing it. Else we will call our next release 2.23.4. | ||