IT/ChangeControl: Difference between revisions

Jump to navigation Jump to search
Line 44: Line 44:


==Submitting a Change Request==
==Submitting a Change Request==
* File a bug in Server Operations: Change Requests
* Include the following:
** data, time, duration of maintenance
** system(s) affected
** end-user impact
** maintenance plan and timeline (link to a wiki or etherpad is fine)
** rollback plan / rollback point (at which point will you determine to roll back)
** notification mechanisms
** who will be point, who else will be involved


= CAB Approval Process=
= CAB Approval Process=