| Line 26: | Line 26: | ||
* Iteration #6: [https://bugzilla.mozilla.org/show_bug.cgi?id=855905 April 17, 2013 - April 30, 2013] | * Iteration #6: [https://bugzilla.mozilla.org/show_bug.cgi?id=855905 April 17, 2013 - April 30, 2013] | ||
<p> </p> | <p> </p> | ||
* Team completed '''75 story points''' across '''25 features''' at the conclusion of Iteration #5 - a '''19% increase in performance''' from the previous iteration. | |||
* Team has established a new average velocity rate of '''47 story points per iteration''' at the conclusion of Iteration #5 - a '''17% increase in performance''' from the previous iteration. | |||
* Overall performance gain in story points and velocity at the conclusion of Iteration #5 has resulted in a new production forecast release of '''December 23, 2013''' - a '''reduction of 3 iterations''' from the previous release update. | |||
* Product Manager review of V1 Release List resulted in the removal of '''9 Feature Stories to V2.''' | |||
* At the conclusion of Iteration #6 the project will have acquired enough data to present three release forecast scenarios: Worst, Expected and Best case. | |||
<p> </p> | <p> </p> | ||
====Iteration Performance Summary==== | ====Iteration Performance Summary==== | ||