Unified Telemetry status report October 7, 2015

Overall Project Health

Last week: Yellow

This week: Green

Exec Summary

  • Stakeholders have agreed to go 100% for both FHR V2 and Unified Telemetry in r42, then turn off FHR V2 in r43
  • Validation project becomes Data Continuity project; focus moves to building the executive dashboard from both sources of data (v2 and v4)
  • 5% release data from 42 is flowing and available for analysis in Spark. 5% release data not yet available in telemetry dashboard
  • Team works towards a late october unified telemetry presentation to executive stakeholders
  • Building a roadmap and documenting the pipeline as a product (how other groups in Mozilla will engage with the pipeline)

Risks/Issues

Description of Risks/Issues State Owner Plan to Resolve/Mitigation Target Date
V4 data validation Open Sam Waiting for more data; blocked on V2 outage. https://docs.google.com/document/d/1rvbCyVSzBsexer-0G7HdR_l1DczKAJdjzChxv0MjYco/ 10/10
Data continuity across V2/V4 Open Katie/Mark/Trink Plan, Metabug 11/2
Legal review Open BDS/Legal Meeting between groups 10/10
QA sign off (functional, load) Done Stuart Telemetry/Testing 8/24
Operations - data retention requirements Open Travis/Katie Eng team owes ops a doc defining ping types and data retention requirements 10/10
Remote about:healthreport content In progress Georg Kicked off localization. 11/2
Budget, size of UT pings In progress Mark/BDS Waiting for release data to spot any problems. https://metrics.services.mozilla.com/telemetry-budget-dashboard/ 8/10
Analysis difficulty Open Katie/tbd Roadmap has several items related to this, need to consolidate as a project 11/2
Access to the 5% sample Done Sam/Roberto Sam is using sample for Addons analysis 8/10

Accomplished for Last Period

please see http://benjamin.smedbergs.us/weekly-updates.fcgi/project/firefox-measurement

Project Mgt

  • completed sprint 1 for client and pipeline

Planned for Next Period

please see http://benjamin.smedbergs.us/weekly-updates.fcgi/project/firefox-measurement

  • Continue work on validation doc (tentative date for presentation to executives is October 13)
  • Meeting with Heather Crince on ramp up and legacy pipeline issues
  • sprint 2 in progress

meetings with other teams

Team initial sit down (informal) second meeting (formal) PRD? notes
iOS done TBD Barb working on PRD Dev track started
loop/hello Done TBD unknown if required Create UT data set
Fennec done done

Requests from other teams

Description State Owner Notes Target Date
FireFox OS In process Mark App/FTU pings in pipeline; next step is to load redshift tables Q4
Hello In process Katie Creating a derived stream: https://bugzilla.mozilla.org/show_bug.cgi?id=1181876 Q4
FxA Activity Event data for retention metrics In process whd Initial data set made available, still need to automate: https://bugzilla.mozilla.org/show_bug.cgi?id=1207015 Q4