Revision as of 17:38, 8 February 2011
The Milestones
2.4.1, Jan 6
- General bug fixing.
- Papercuts from the end of Q4.
2.4.2, Jan 18
- Search result improvements.
2.4.3, Jan 25
- Army of Awesome localization.
2.5, Feb 15
- Theme.
- Bring the new theme to the whole site.
- Refactor and organize templates.
- Notifications.
- Replace notification subsystem with one that works.
2.6, March 8
- Mobile experience
2.6.1, March 15
"2.7", late Q1/early Q2
- User Dashboards.
- First half of the Users and Groups PRD.
"2.8", Q2
- Group Dashboards.
- Second half of the Users and Groups PRD.
- May be a series of 2.6.x releases. Version numbers don't make sense for web sites.
Sketch of Q1 Timeline
Read top to bottom.
| Date (approx) | Milestone | Ongoing Work | |||
|---|---|---|---|---|---|
| 3 January | 2.4.1 - bugs | Notifications | R&B | Search | |
| 14 January | 2.4.2 - search | AoA L10n | Theme | ||
| 25 January | 2.4.3 - AoA | Theme | |||
| 7 February | 2.5 - Notifications and Theme | User Dash | |||
| 28 February | 2.6 - Mobile | Mobile | R&B | ||
| ~30 March | ~2.7 - User Dashes | User Dashes | |||
R&B: "Refactoring and bugfixing"
*Group Dashes
This is not necessarily a big, monolithic milestone. If the architecture ends up roughly how I expect, we should be able to ship several small releases as we finish various group dashboards and flip them on one at a time.
Continuous Deployment
We haven't yet hammered out the steps we need to take this quarter to reach our CD goal. The refactoring time will largely be used for this, but the targets aren't here yet.