Firefox OS/OneDotFourTracking: Difference between revisions
Jump to navigation
Jump to search
Praghunath (talk | contribs) |
Praghunath (talk | contribs) |
||
| Line 69: | Line 69: | ||
</tr> | </tr> | ||
<tr> | <tr> | ||
<td>QA | <td>QA END to END TEST RUN</td> | ||
<td>3/17/2014 - 3/28/2014</td> | <td>3/17/2014 - 3/28/2014</td> | ||
<tr> | |||
<td>LOCALIZATION BUG FIXES COMPLETE </td> | |||
<td>03/31/2014 – 04/21/2014</td> | |||
</tr> | </tr> | ||
<tr> | |||
<td>RTP - RELEASE TO PARTNER</td> | |||
<td>4/25/2014</td> | |||
</tr> | |||
<tr> | |||
<th>FEATURE LIST WALK THROUGH</th> | |||
<th>3/17/2014</th> | |||
#Feature list walk through 1.4 :: 3/17/2014 | |||
#Convergence branch creation :: 3/17/2014 | |||
#Convergence done :: 4/25/2014 | |||
#QC CS :: Currently 5/15 (will negotiate to 06/20/2014) | |||
#Regular blocker triage with RM :: 3/17/14 onwards | |||
#No more approvals on gaia flags :: 3/24/2014 | |||
#End to end regression 2 :: 4/15-14 - 4/25/14 (sprint 6) | |||
#End to end regression 3 :: post RTP -- on 1.4 branch | |||
#Company Bug Bash :: week of 4/15/14 (sprint 6) | |||
#Recommended IOT test start/ Customization testing complete :: 4/25/14 onwards | |||
#Recommended final IOT testing :: based on partner | |||
#TA :: 11/20/2014 | |||
</table> | </table> | ||
Revision as of 02:47, 1 February 2014
1.4 ROADMAP
https://wiki.mozilla.org/B2G/Roadmap#Key_Focus_1.4_Features
1.4 Schedule
- Milestones Schedule
- Sprint 1 – feature dev :: 2/3/14 – 2/14/14
- Sprint 2 – feature dev :: 2/17/14 – 2/28/14
- Sprint 3 – feature dev :: 3/3/14 – 3/14/14
- Sprint 4 – Planning (1.5) :: 3/17/14 – 3/28/14
- Sprint 4 - 1.4 stabilization begins
- Sprint 5 – stabilization :: 4/1/14 – 4/11/14
- Sprint 6 – stabilization :: 4/15/14 – 4/25/14
- Internal feature complete :: 3/14/2014
- Hard string Freeze :: 3/28/2014
- QA end to end test run :: 3/17/14 - 3/28/14 (sprint 4)
- Localization bug fixes complete :: 03/31/2014 – 04/21/2014
- Localization testrun :: 4/1/14 - 4/11/14 (sprint 5)
- RTP - Release to Partner :: 4/25/2014
- Feature list walk through 1.4 :: 3/17/2014
- Convergence branch creation :: 3/17/2014
- Convergence done :: 4/25/2014
- QC CS :: Currently 5/15 (will negotiate to 06/20/2014)
- Regular blocker triage with RM :: 3/17/14 onwards
- No more approvals on gaia flags :: 3/24/2014
- End to end regression 2 :: 4/15-14 - 4/25/14 (sprint 6)
- End to end regression 3 :: post RTP -- on 1.4 branch
- Company Bug Bash :: week of 4/15/14 (sprint 6)
- Recommended IOT test start/ Customization testing complete :: 4/25/14 onwards
- Recommended final IOT testing :: based on partner
- TA :: 11/20/2014
- Feature list walk through 1.4 :: 3/17/2014
- Convergence branch creation :: 3/17/2014
- Convergence done :: 4/25/2014
- QC CS :: Currently 5/15 (will negotiate to 06/20/2014)
- Regular blocker triage with RM :: 3/17/14 onwards
- No more approvals on gaia flags :: 3/24/2014
- End to end regression 2 :: 4/15-14 - 4/25/14 (sprint 6)
- End to end regression 3 :: post RTP -- on 1.4 branch
- Company Bug Bash :: week of 4/15/14 (sprint 6)
- Recommended IOT test start/ Customization testing complete :: 4/25/14 onwards
- Recommended final IOT testing :: based on partner
- TA :: 11/20/2014
| MILESTONE | SCHEDULE |
|---|---|
| SPRINT 1 DEV | 2/3/14 – 2/14/14 |
| SPRINT 2 DEV | 2/17/14 – 2/28/14 |
| SPRINT 3 DEV | 3/3/14 – 3/14/14 |
| SPRINT 4 PLANNING | 3/17/14 – 3/28/14 |
| SPRINT 5 STABILIZATION | 4/1/14 – 4/11/14 |
| SPRINT 6 STABILIZATION | 4/15/14 – 4/25/14 |
| INTERNAL FEATURE COMPLETE | 3/14/2014 |
| HARD STRING FREEZE | 3/28/2014 |
| QA END to END TEST RUN | 3/17/2014 - 3/28/2014 |
| LOCALIZATION BUG FIXES COMPLETE | 03/31/2014 – 04/21/2014 |
| RTP - RELEASE TO PARTNER | 4/25/2014 |
| FEATURE LIST WALK THROUGH | 3/17/2014 |