IT/Production Acceptance/all.html redesign
< IT | Production Acceptance
Jump to navigation
Jump to search
Start of project
- Name each of the following:
- Project sponsor: Laura Mesa
- Main IT contact: ?
- Main WebDev contact: Wil Clouser
- Main QA contact: Stephen Donnor
- Main third party contact: Steven Garrity
- Final application owner/maintainer: Laura Mesa
- Outline the following:
- Overall goal of the project
- Any pre-requisites needed (technology, server capacity, staffing, monitoring, response time, etc)
- Initial timeline
- Dec 1 - Final design and PSD original files
- Dec 30 - Options 2 and 3 code complete
- Jan 27 - Option 1 code complete
- Feb 10 (mid-Feb) - QA complete
- Feb 24 - A/B Testing starts
- March 3 - A/B Testing ends
- March 10 - Analysis complete
- March 31 - Launch final design
- External dependencies
- Dev environment specs
- Does this project use any plugins or proprietary technology?
Staging Signoff
In order to get an app into staging, the following should be completed:
- Code committed to Mozilla source control and tagged
- Initial architecture review by IT and WebDev
- Plugin/tech review by Evangelism
- Site must be password protected
- Review timeline to go live
- Review any production requirements so IT can order any new hardware needed
Production Signoff/Launch
- Final WebDev signoff
- Final IT signoff
- Final QA signoff
- Operations documents filled for support & any training complete
- Monitors in place