Meeting Topics

  • Mobile baby, yeah! \o/
  • Basecamp

Dietrich

  • PTO - until July 2nd.

Erin

Lawrence

  • Basecamp
    • Working with GFX/Layout and WebAPI teams to define scope/work, identify dependencies, and draft schedule.
  • Kilimanjaro
    • Triage seems to be primarily focused around Apps, Marketplace, and AItC, with some Identity. Not surprising as B2G is handled as part of basecamp triage and there aren't a lot of requirements on desktop and mobile outside of Apps.
  • Mobile Web Compat
    • Lots of meeting attendance but little resource to do leg work. Need to engage broader Mozilla community.
  • Silent update
    • Background Updates preffed on for Windows on Aurora. \o/
  • Snappy
    • Moving more slowly as resource have been pulled for various other priorities. Working on resource contention issues.

Martin

Michael

Sheila