Unified Telemetry status report July 17, 2015

Overall Project Health

Green - r41 is go live for unified Telemetry. All issues triaged and assigned milestones. Dev Team continues to focus on data validation.

Exec Summary

  • Client work delayed this week by sick time.
  • Working toward data validation milestone on July 30: http://mzl.la/1J2OdZA
  • Pipeline scaling work to be completed by July 30(?)
  • <tools>
  • Ongoing planning on FHR V2/V3 historic pipeline migration link to status here.

Risks/Issues

Description of Risks/Issues State Owner Plan to Resolve/Mitigation Target Date
Data integrity between V2/V4 and V4 internal data consistency Open Brendan/Sam Investigation in progress. Added resources (Sam). https://etherpad.mozilla.org/fhr-v4-validation 7/30
Data continuity across V2/V4 Open Katie/Mark/Trink Mark writing up plan from Whistler; metrics team specifying data sets and reviewing "executive" data set. https://bugzilla.mozilla.org/show_bug.cgi?id=1182684 7/23
Legal review Open BDS/Legal Meeting between groups 8/04
QA sign off (functional, load) Open Stuart Working with QA on creating test cases/test plans 8/04
Operations - data retention requirements Open Travis/Katie Eng team owes ops a doc defining ping types and data retention requirements 8/04
Operations - analysis tools & microservices Open Travis/Mark/Roberto Architecture/Data flow diagram; meeting next Monday (7/13) 8/04
Data loss incident Fixed mreid/whd/trink Tee server needs to return error status from old or new. Added Ops resources (Daniel Thornton). 7/15
Remote about:healthreport content Open Katie/Georg Made a request to Laura Thomson for help 8/04
Budget, size of UT pings Open Mark/BDS https://bugzilla.mozilla.org/show_bug.cgi?id=1182693 8/04
Analysis difficulty Open Katie/tbd No plan yet, aside from ongoing work on tools 8/04

Accomplished for Last Period

Engineering & Ops

QA

  • test cases, bug closing

Project management

  • meeting, emails, hand waving

Planned for Upcoming Period

Engineering

Ops

  • Meeting to go over Telemetry tools/microservices production deployment
  • Continued work on scaling for release loads
  • data bricks investigation (big jobs on big clusters) - cost, resourcing etc

Performance

  • automate spark

QA

  • closing bugs
  • test suite creation
  • finalizing long term QA engagement (softvision engagement, tooling asks for CI loop based testing)

Project Management

  • Finish triage of bugs
  • remainder of release tasks scheduled

Outstanding requests not yet road mapped into a release

Description State Owner Plan to Resolve/Mitigation Target Date
FireFox OS - app pings Open Katie Need to schedule and understand impact on project TBD
histograms for loop/hello Open Katie Need to schedule and understand impact on project TBD