TestEngineering/UI/AMO/5.0.6 Test Plan

From MozillaWiki
< TestEngineering‎ | UI
Revision as of 23:05, 11 May 2009 by Krupa (talk | contribs)
Jump to navigation Jump to search

CTAW project page

AMO 5.0.6 test plan


MOCK-UPS/Specs: http://people.mozilla.com/~jscott/bandwagon/clearleft/v11/

STAGING SERVER: preview.addons.mozilla.org

Acceptance doc: ?

Planned Release date:

   * Release is currently scheduled for June 2009

QA Resources:

   * Stephen Donner (irc:stephend)
   * Krupa Raj (irc:krupa) 

QA Support Level:Level 1.

See all our Support levels

QA will cover:

  • Detailed Browser Compatibility testing
  • Doctype validation
  • Basic Formatting and Appearance
  • Link validation
  • User interactions
   o Need to specify details here           
  • JavaScript-disabled testing for: (1/4 day)
   o Front page
   o Browsing by category 

Other:

  • Accessibility testing-Marco?
  • Localization testing-???[May have to involve the Localization community early on]

What is out of scope:

  • Unit Testing
  • Performance testing (Load, Volume, Stress)
  • White Box testing
  • Security testing


Team needs to help cover:

   * Verifying copy is correct
   * Ensuring that final designs are correct 

Entry and Exit Criteria:

   * Entry criteria:
         o Mocks/Specs are made available to the QA team
         o QA team has access to staging server
         o CTAW website is ready for testing            


   * Exit Criteria
         o No crashing bugs.
         o All features under the scope of this release are functional.
         o All P0 and P1 bugs are either fixed or deferred.
         o All P0/P1 fixes are verified by QA and marked as such in Bugzilla.
         o QA has verified that the fixes have not caused major regression. 

Test deliverables:

   * Test Plan
   * Bug reports
   * Interim status updates 

Assumptions and Risk Management:

   * Assumptions:
         o There is no schedule slippage from development.
         o No feature creep. 
         o QA has the latest specs;QA is always informed of any changes to the project 


   * Risks and their management:
         o Need to fill information here