| Line 17: | Line 17: | ||
* The development effort needed to support user testing requires an expansion of the project's scope. | * The development effort needed to support user testing requires an expansion of the project's scope. | ||
* The scope expansion has changed the project’s metrics as follows: | * The scope expansion has changed the project’s metrics as follows: | ||
** Backlog Size: From 58 total bugs to 70 total bugs. | ** '''Backlog Size''': From 58 total bugs to 70 total bugs. | ||
** Remaining Work: From 10 bugs to 22 bugs. | ** '''Remaining Work''': From 10 bugs to 22 bugs. | ||
** Percentage Complete: From 90% to 80%. | ** '''Percentage Complete''': From 90% to 80%. | ||
** Forecast Completion Date: From August 17 to September 28. | ** '''Forecast Completion Date''': From August 17 to September 28. | ||
* View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog. | * View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog. | ||
[[File:WPD CurrentUpdateNow.png|frame|center|Updated Weekly. Current Update - Tuesday, July 24.]] | [[File:WPD CurrentUpdateNow.png|frame|center|Updated Weekly. Current Update - Tuesday, July 24.]] | ||