==== July 24 Update ==== | ==== July 24 Update ==== | ||
<p> </p> | <p> </p> | ||
* The | * The goal of Milestone 3 to support user testing requires an expansion of the project's scope resulting in extended development effort. | ||
* Our MVP delivery date for Q1/2019 is not impacted. | |||
* The scope expansion has changed the project’s metrics as follows: | * The scope expansion has changed the project’s metrics as follows: | ||
** '''Backlog Size''': From 58 total bugs to 70 total bugs. | ** '''Backlog Size''': From 58 total bugs to 70 total bugs. | ||