Website/Sprints/PluginProblem: Difference between revisions

From MozillaWiki
Jump to navigation Jump to search
Line 9: Line 9:


Scope:  
Scope:  
*TBD
 
*Four week project to finish phase 1 of the Plug-In project.
**


Schedule:  
Schedule:  
*August 18th-25th
**TRO works on first front end Mock-Up
*August 24th-September 16th
**Database development
*September 1st-7th
**Page implementation
*September 17th-25th
**QA and bug fixes
*September 25th-30th
**Push page live


*August 18-24: TRO works on first front end Mock-Up/Final Page
Due Dates:
*August 25-September 8
*August 24th
**Copy Finished
*August 25th
**First Mock-up of Page design
*August 31st
**Final Page design
*September 7th
**Page implementation done
*September 16th
**Database developed
*September 25th
QA finishes testing
*September 30th
**Page Live


Team: (please add more names as needed)  
Team: (please add more names as needed)  
Line 26: Line 51:
*Laura Mesa  
*Laura Mesa  
*Alix Franquet
*Alix Franquet
Bugs: (Please document all bugs filed here.)

Revision as of 22:59, 18 August 2009

Plug-In Problem

Goal:

What It Is:

Scope:

  • Four week project to finish phase 1 of the Plug-In project.

Schedule:

  • August 18th-25th
    • TRO works on first front end Mock-Up
  • August 24th-September 16th
    • Database development
  • September 1st-7th
    • Page implementation
  • September 17th-25th
    • QA and bug fixes
  • September 25th-30th
    • Push page live

Due Dates:

  • August 24th
    • Copy Finished
  • August 25th
    • First Mock-up of Page design
  • August 31st
    • Final Page design
  • September 7th
    • Page implementation done
  • September 16th
    • Database developed
  • September 25th

QA finishes testing

  • September 30th
    • Page Live

Team: (please add more names as needed)

  • Austin King
  • Les Orchard
  • silverorange
  • Mike Morgan
  • John Slater
  • TRO
  • Laura Mesa
  • Alix Franquet

Bugs: (Please document all bugs filed here.)