Unified Telemetry status report October 7, 2015

Overall Project Health

Last week: Yellow

This week: Green

Exec Summary

  • Stakeholders have agreed to go 100% for both FHR V2 and Unified Telemetry in r42, then turn off FHR V2 in r43
  • Validation project becomes Data Continuity project; focus moves to building the executive dashboard from both sources of data (v2 and v4)
  • 5% release data from 42 is flowing and available for analysis in Spark. 5% release data not yet available in telemetry dashboard
  • Team works towards an October 13th unified telemetry presentation for executive stakeholders
  • Building a roadmap and documenting the pipeline as a product (how other groups in Mozilla will engage with the pipeline)

Risks/Issues

Description of Risks/Issues State Owner Plan to Resolve/Mitigation Target Date
V4 data integrity Open Brendan/Sam Investigation in progress. https://docs.google.com/document/d/1rvbCyVSzBsexer-0G7HdR_l1DczKAJdjzChxv0MjYco/ 10/10
Data continuity across V2/V4 Open Katie/Mark/Trink Plan, Metabug 11/2
Legal review Open BDS/Legal Meeting between groups 10/10
QA sign off (functional, load) Done Stuart Telemetry/Testing 8/24
Operations - data retention requirements Open Travis/Katie Eng team owes ops a doc defining ping types and data retention requirements 10/10
Remote about:healthreport content Open Georg Needs test, localization and deployment 11/2
Budget, size of UT pings In process Mark/BDS https://metrics.services.mozilla.com/telemetry-budget-dashboard/ 8/10
Analysis difficulty Open Katie/tbd Spark training; need comprehensive plan 11/2
Access to the 5% sample In process Sam/Roberto https://bugzilla.mozilla.org/show_bug.cgi?id=1191789 Sams bug 8/10

Accomplished for Last Period

please see http://benjamin.smedbergs.us/weekly-updates.fcgi/project/firefox-measurement

Project Mgt

  • completed sprint 1 for client and pipeline

Planned for Next Period

please see http://benjamin.smedbergs.us/weekly-updates.fcgi/project/firefox-measurement

  • Continue work on validation doc (tentative date for presentation to executives is October 13)
  • Meeting with Heather Crince on ramp up and legacy pipeline issues
  • sprint 2 in progress

meetings with other teams

Team initial sit down (informal) second meeting (formal) PRD? notes
iOS done TBD Barb working on PRD Dev track started
loop/hello Done TBD unknown if required Create UT data set
Fennec done done
Synch
FxA

Outstanding requests not yet road mapped into a release

Description State Owner Plan to Resolve/Mitigation Target Date
FireFox OS - app pings Open Katie included in road mapping in process
histograms for loop/hello Open Katie Need to schedule and understand impact on project TBD

Important Links/References