Support/Goals/2011Q3/Fx Features
From MozillaWiki
< Support | Goals/2011Q3
A page to track the progress of these features.
Fix Profile
- [DONE] 2011-07-15 Figure out how to get planning started
- Asa said he'll push this in the triage meeting tomorrow. I let him know that I'll be available to help get anything done or arrange anything that needs to be arranged to keep things on track for landing this quarter.
- [DONE] 2011-08-30 Complete planning
- 2011-08-05 Asa says they are looking for an engineer to take this on.
- 2011-08-23 Sent out new email to Asa and Johnathan to try to get everyone on the same page and see if we can get this feature picked up.
- 2011-08-26 Asa: "This is in Product top priorities. We will be meeting with Johnath next week hopefully to re-connect on Product and Engineering communications."
- This is just waiting to be done. It's #6 in the list of P1s. Nothing else to do at the moment but wait.
- [MISSED] 2011-09-26 Land in Nightly (Firefox 9)
- Latest estimate is that an engineer will pick this up by 10/7/2011
Broken installs
- [DONE] 2011-07-15 Meet with engineering to re-define plan.
- [DONE] 2011-07-29 Get script from Rob Strong and begin collecting data.
- 2011-08-04 Rob Strong says the script will be done no later than 08-09-2011.
- I got the script on 2011-08-12 and wrote an article for it (deleted and saved locally). The script will need some changes and security review before we can host it and publish the article.
- [MISSED] 2011-08-26 Complete script changes and security review - ready to start working with users.
- Rob Strong says he should have the updated script late today (8/23). I'll collect it and changes to the article and submit to security and sumodev asap.
- 2011-08-29 New script is done but we're waiting on email forwarding and the ability for sumodev to push a new update as often as every day while we test the program.
- [MISSED] 2011-09-13 Complete script changes and security review - ready to start working with users.
- [DONE] SUMO infrastructure (download page and file hosting) won't be done until 9/13.
- Rob Strong is heading up the silent install team. Work has stalled while that gets started.
- [MISSED] 2011-09-27 Complete collecting data and determine next steps.
Clear Cookies & Cache
- [DONE] 2011-07-22 Meet with UX to get input on defining the feature
[NEW] 2011-07-22 Meet with Engineering to get input on defining the feature- [DONE] 2011-07-29 Define the feature and create a feature page
- [DONE] 2011-08-12 Meet with Engineering to get input on feature design
- [DONE] 2011-09-13 Complete feature design
- Emailed Alex Faaborg (8/23) to see if he has time to pick this up.
- Lots of email discussion. Seems like this feature could also be split.
- 9/7 Created new (more focused) feature page and put in in the feature inbox for triage.
- [MISSED] 2011-09-26 Complete feature planning
- Latest estimate is that these will get triaged sometime in late Oct. or early Nov.
- Complete feature planning probably shouldn't be part of a goal - we have no control over it as it's dependent on when the feature begins being worked on.
Help when Fx can't connect
- [DONE] 2011-07-22 Meet with UX to get input on defining the feature
[NEW] 2011-07-22 Meet with Engineering to get input on defining the feature- [DONE] 2011-07-29 Define the feature and create a feature page
- [DONE] 2011-08-12 Meet with Engineering to get input on feature design
- Johnathan says, this feature "needs more careful scoping - there are two or three features in there, unified by a central goal but nonetheless distinct. We should figure out what the smallest thing is that we can do to help people first, build a specific and well-defined feature page around that, and get it staffed. Then the next one. Then the next one."
- [DONE] 2011-09-13 Complete feature design
- Emailed Alex Faaborg (8/23) proposing a way to break this into two features.
- 9/7 Created new (more focused) feature page and put in in the feature inbox for triage.
- [MISSED] 2011-09-26 Complete feature planning
- Latest estimate is that these will get triaged sometime in late Oct. or early Nov.
- Complete feature planning probably shouldn't be part of a goal - we have no control over it as it's dependent on when the feature begins being worked on.