= Milestones = | = Milestones = | ||
= Milestones = | |||
== Beta 2 == | |||
* '''Status''': Active | |||
* '''Start Date''': | |||
* '''Forecast Completion Date''': | |||
* '''Actual Completion Date''': | |||
=== All MVP Bugs === | |||
* [https://mzl.la/3n8Y8EV View Bugzilla Query]. | |||
<bugzilla> | |||
{ | |||
"whiteboard": "[puppeteer-beta2-mvp]", | |||
"include_fields":"id, summary, status, assigned_to, priority" | |||
} | |||
</bugzilla> | |||
=== All Reserve Bugs === | |||
* [https://mzl.la/36qRcgD View Bugzilla Query]. | |||
<bugzilla> | |||
{ | |||
"whiteboard": "[puppeteer-beta2-reserve]", | |||
"include_fields":"id, summary, status, assigned_to, priority" | |||
} | |||
</bugzilla> | |||
== Beta == | == Beta == | ||
* ''' | * '''Status''': Completed | ||
* ''' | * '''Start Date''': December 13, 2019 | ||
* '''Forecast Completion Date''': June 5, 2020 | |||
* '''Actual Completion Date''': May 20, 2020 | |||
* For details view the [https://docs.google.com/spreadsheets/d/1CAMaBlX6n5nKvKuBNUcmTZSaPaiGVvIT07u39lkirAE/edit?usp=sharing Project Tracking Dashboard]. | |||
=== All MVP Bugs === | |||
* [https://mzl.la/2VNpkNS View Bugzilla Query]. | |||
<bugzilla> | <bugzilla> | ||
{ | { | ||
"whiteboard": "puppeteer- | "whiteboard": "[puppeteer-beta-mvp]", | ||
"include_fields": "id, | "include_fields":"id, summary, status, assigned_to, priority" | ||
} | } | ||
</bugzilla> | </bugzilla> | ||
=== All | === All Reserve Bugs === | ||
* [https://mzl.la/2YbT0pA View Bugzilla Query]. | |||
<bugzilla> | <bugzilla> | ||
{ | { | ||
"whiteboard": "puppeteer-beta", | "whiteboard": "[puppeteer-beta-reserve]", | ||
"include_fields": "id, | "include_fields":"id, summary, status, assigned_to, priority" | ||
} | } | ||
</bugzilla> | </bugzilla> | ||
== Alpha == | == Alpha == | ||
* ''' | * '''Status''': Completed | ||
* | * '''Start Date''': November 22, 2019 | ||
* '''Forecast Completion Date''': December 20, 2019 | |||
* '''Actual Completion Date''': December 12, 2019 | |||
* For details view the [https://docs.google.com/spreadsheets/d/169Wvq_NGcUJjPDeX_xPjffs6__tIlQDtKyemqlor3QI/edit?usp=sharing Project Tracking Dashboard]. | |||
* [https://mzl.la/2WgDg1m View Bugzilla Query]. | |||
<bugzilla> | <bugzilla> | ||
{ | { | ||
"whiteboard": "puppeteer-alpha", | "whiteboard": "[puppeteer-alpha]", | ||
" | "priority": ["P1"], | ||
" | "include_fields":"id, summary, status, assigned_to, priority" | ||
} | } | ||
</bugzilla> | </bugzilla> |
Latest revision as of 20:09, 26 February 2021
Milestones
Milestones
Beta 2
- Status: Active
- Start Date:
- Forecast Completion Date:
- Actual Completion Date:
All MVP Bugs
60 Total; 1 Open (1.67%); 59 Resolved (98.33%); 0 Verified (0%);
All Reserve Bugs
No results.
0 Total; 0 Open (0%); 0 Resolved (0%); 0 Verified (0%);
Beta
- Status: Completed
- Start Date: December 13, 2019
- Forecast Completion Date: June 5, 2020
- Actual Completion Date: May 20, 2020
- For details view the Project Tracking Dashboard.
All MVP Bugs
50 Total; 0 Open (0%); 50 Resolved (100%); 0 Verified (0%);
All Reserve Bugs
16 Total; 0 Open (0%); 16 Resolved (100%); 0 Verified (0%);
Alpha
- Status: Completed
- Start Date: November 22, 2019
- Forecast Completion Date: December 20, 2019
- Actual Completion Date: December 12, 2019
- For details view the Project Tracking Dashboard.
- View Bugzilla Query.
28 Total; 0 Open (0%); 28 Resolved (100%); 0 Verified (0%);